Cemerlang Mega Projects

LIGHT RAIL TRANSIT LINE 3 (LRT3) FROM BANDAR UTAMA TO JOHAN SETIA (PACKAGE GS-02, GS-03)

Concrete blocks were placed onto the segment for testing in accordance with DOSH requirements. The tests were conducted in two stages: the first stage involved adding 10% additional weight (Dynamic test), and the second stage required adding 25% additional weight (Static test).

Test on the Lifting Frame were witnessing by the DOSH official

Segment were delivered by low loader to the position under the hook, remaining work to be carry out by Cemerlang Mega operation team

The installation process was divided into two distinct steps. The segment located further down the chainage, towards the land side, was successfully installed during the daytime. Conversely, the segment situated towards the up chainage, closer to the expressway, was scheduled for installation during the nighttime, specifically within the designated road closure timeframe

Employing an Underslung Lifting Frame ensures the consistent delivery of your segment to a predetermined location in proximity to the pier, irrespective of the ongoing work progress. The lifting frame will not only hoist the segment but also reposition it along the bridge alignment to facilitate precise installation.

Constructing bridges in urban conditions presents significant challenges. Hidden utilities pose obstacles to earthwork and foundation efforts, while existing roads and bridges undoubtedly impede progress. These factors necessitate additional precautionary measures to ensure smooth operations



The Lifting Frame was specifically designed and fabricated for deployment across two distinct projects: MRT-V204 and LRT-3, encompassing three different types of segments. The solution offered by Cemerlang Mega not only grants flexibility to the Main Contractor but also translates into substantial cost savings in terms of investment

The Lifting Frame was specifically designed and fabricated for deployment across two distinct projects: MRT-V204 and LRT-3, encompassing three different types of segments. The solution offered by Cemerlang Mega not only grants flexibility to the Main Contractor but also translates into substantial cost savings in terms of investment



The presence of an adept and seasoned team is paramount when considering the execution of any endeavor, as it significantly contributes to both the safety of the mission and the overall success of the operation. Their collective expertise, honed through years of practical experience, ensures a heightened level of preparedness, the ability to navigate challenges effectively, and the implementation of well-informed strategies that lead to favorable outcomes. In essence, the foundation of success and safety is firmly rooted in the capabilities and proficiency of an experienced team